CN Railroad has shared an update concerning the Oliver Bridge construction.  The railroad company has been working on the Oliver Bridge in a project that will help the company continue and expand it's operations all summer. 

At this point, the railway deck is 72% complete, and the remaining material needed for the other 28% of decking have arrived and are on site.  The Oliver Bridge will remained closed Monday - Friday from 8 to 5 until November 17th.  That date is subject to change depending on the progress made.

You can find more information on the project by visiting the MNDOT project page.